nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #758

Which is a purpose of the Directing a Project process?

The correct answer is D. Delegate day-to-day management of the project to the Project Manager. See the full explanation below for the reasoning.

Question

Which is a purpose of the Directing a Project process?

Options

  • ACreate and authorize the project mandate
  • BEnsure that work on products allocated to the team is authorized and agreed
  • CControl the day-to-day running of the project
  • DDelegate day-to-day management of the project to the Project Manager

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    18% (7)
  • C
    8% (3)
  • D
    71% (27)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice