At which point should a project be terminated?

The correct answer is D. A project should be terminated when the Project Board decides that the project is no longer viable. See the full explanation below for the reasoning.

Question

At which point should a project be terminated?

Options

  • AA project should be terminated once it is predicted to exceed the project tolerance
  • BA project should be terminated if the Project Manager or a member of the Project Board resigns
  • COnce a project commences, it should continue to completion
  • DA project should be terminated when the Project Board decides that the project is no longer viable

How the community answered

(29 responses)
  • A
    14% (4)
  • B
    3% (1)
  • C
    10% (3)
  • D
    72% (21)

Community Discussion

No community discussion yet for this question.