PRINCE2-FOUNDATION · Question #74

Controlling a Stage describes the day-to-day work of the Project Manager. Which of the following statements is false?

The correct answer is D. All of Controlling a Stage is used in a time-driven manner. See the full explanation below for the reasoning.

Question

Controlling a Stage describes the day-to-day work of the Project Manager. Which of the following statements is false?

Options

  • AIn Controlling a Stage, the Stage Plan is updated with actuals and progress is checked against the
  • BControlling a Stage drives Managing Product Delivery
  • CThe Project Manager uses the process Controlling a Stage to manage any deviations from Stage or
  • DAll of Controlling a Stage is used in a time-driven manner

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    3% (1)
  • D
    81% (25)

Community Discussion

No community discussion yet for this question.