The Project Mandate is usually derived from:

The correct answer is D. Programme or corporate management? See the full explanation below for the reasoning.

Question

The Project Mandate is usually derived from:

Options

  • AA sketch on the back of an envelope?
  • BThe very first PRINCE2 process?
  • CA PRINCE2 project think-tank of the Project Manager, other team members and the Project Board?
  • DProgramme or corporate management?

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    5% (2)
  • C
    14% (5)
  • D
    73% (27)