The Project Mandate is usually derived from:
The correct answer is D. Programme or corporate management? See the full explanation below for the reasoning.
Question
The Project Mandate is usually derived from:
Options
- AA sketch on the back of an envelope?
- BThe very first PRINCE2 process?
- CA PRINCE2 project think-tank of the Project Manager, other team members and the Project Board?
- DProgramme or corporate management?
How the community answered
(37 responses)- A8% (3)
- B5% (2)
- C14% (5)
- D73% (27)