PRINCE2-FOUNDATION · Question #749
PRINCE2-FOUNDATION Question #749: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #749. The question stem and answer options stay visible for context.
Question
Which is a purpose of the Closing a Project process?
Options
- AAuthorize the final stage of the project
- BConfirm that all benefits defined in the Business Case have been achieved
- CRecognize whether objectives set out in the original Project Initiation Documentation have been
- DDelegate day-to-day management of the end of the project to the Project Manager
Unlock PRINCE2-FOUNDATION to see the answer