PeopleCert
PRINCE2-FOUNDATION · Question #748
PRINCE2-FOUNDATION Question #748: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #748. The question stem and answer options stay visible for context.
Question
Which is an objective of the Closing a Project process?
Options
- APrepare the plan for the next stage
- BAssess any benefits that have already been realized
- CProduce a Benefits Review Plan to identify what benefits are expected
- DCheck that all benefits are realized before closing a project
Unlock PRINCE2-FOUNDATION to see the answer