Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
The correct answer is B. Follow-on action recommendations. See the full explanation below for the reasoning.
Question
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Options
- AOff-specifications
- BFollow-on action recommendations
- CIssue Register
- DRisk Register
How the community answered
(32 responses)- A9% (3)
- B72% (23)
- C3% (1)
- D16% (5)