Which should be funded by a change budget?

The correct answer is A. Increase in agreed scope. See the full explanation below for the reasoning.

Question

Which should be funded by a change budget?

Options

  • AIncrease in agreed scope
  • BInitiation stage
  • CChange Authority
  • DHandover activities

How the community answered

(26 responses)
  • A
    81% (21)
  • B
    4% (1)
  • C
    12% (3)
  • D
    4% (1)