Which should be funded by a change budget?
The correct answer is A. Increase in agreed scope. See the full explanation below for the reasoning.
Question
Which should be funded by a change budget?
Options
- AIncrease in agreed scope
- BInitiation stage
- CChange Authority
- DHandover activities
How the community answered
(26 responses)- A81% (21)
- B4% (1)
- C12% (3)
- D4% (1)
Community Discussion