PRINCE2-FOUNDATION · Question #740

Which should be funded from a change budget?

The correct answer is C. An agreed change to the scope of a project. See the full explanation below for the reasoning.

Question

Which should be funded from a change budget?

Options

  • AThe Starting up a Project process
  • BA fallback plan
  • CAn agreed change to the scope of a project
  • DA change to a plan, within allocated tolerances, due to poor estimating

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    82% (23)
  • D
    7% (2)