PeopleCert
PRINCE2-FOUNDATION · Question #738
What needs to be in place to ensure effective issue and change control?
The correct answer is A. Configuration management system. See the full explanation below for the reasoning.
Question
What needs to be in place to ensure effective issue and change control?
Options
- AConfiguration management system
- BManage by exception
- CQuality planning
- DInformation needs for stakeholders
How the community answered
(37 responses)- A70% (26)
- B8% (3)
- C19% (7)
- D3% (1)
Community Discussion