Question

There are 6 variables involved in all projects. The first 5 are costs, timescales, quality, scope and risk. What is the 6th?

Options

  • AProducts
  • BManagement
  • COutcomes
  • DBenefits

Unlock PRINCE2-FOUNDATION to see the answer

You've previewed enough free PRINCE2-FOUNDATION questions. Unlock PRINCE2-FOUNDATION for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.