PeopleCert
PRINCE2-FOUNDATION · Question #71
There are 6 variables involved in all projects. The first 5 are costs, timescales, quality, scope and risk. What is the 6th?
The correct answer is D. Benefits. See the full explanation below for the reasoning.
Question
There are 6 variables involved in all projects. The first 5 are costs, timescales, quality, scope and risk. What is the 6th?
Options
- AProducts
- BManagement
- COutcomes
- DBenefits
How the community answered
(21 responses)- A5% (1)
- B5% (1)
- C10% (2)
- D81% (17)
Community Discussion