PRINCE2-FOUNDATION · Question #71

There are 6 variables involved in all projects. The first 5 are costs, timescales, quality, scope and risk. What is the 6th?

The correct answer is D. Benefits. See the full explanation below for the reasoning.

Question

There are 6 variables involved in all projects. The first 5 are costs, timescales, quality, scope and risk. What is the 6th?

Options

  • AProducts
  • BManagement
  • COutcomes
  • DBenefits

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    10% (2)
  • D
    81% (17)