PRINCE2-FOUNDATION · Question #72

In the "Plan the Next Stage" activity, which project role is responsible for reviewing the next Stage Plan?

The correct answer is B. Project Assurance. See the full explanation below for the reasoning.

Question

In the “Plan the Next Stage” activity, which project role is responsible for reviewing the next Stage Plan?

Options

  • AProject Manager
  • BProject Assurance
  • CSenior User
  • DCorporate/Programme Management

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    82% (37)
  • C
    2% (1)
  • D
    11% (5)