PRINCE2-FOUNDATION · Question #70
The Project Board has three responsibilities towards the Management of Risk. Which of the following options is the FALSE one?
The correct answer is B. Ensuring that risks are identified, recorded and regularly reviewed. See the full explanation below for the reasoning.
Question
The Project Board has three responsibilities towards the Management of Risk. Which of the following options is the FALSE one?
Options
- ANotifying the Project Manager of any external risk exposure to the project
- BEnsuring that risks are identified, recorded and regularly reviewed
- CMaking decisions on recommended reactions to risk
- DStriking a balance between level of risk and potential benefits
How the community answered
(67 responses)- A9% (6)
- B73% (49)
- C4% (3)
- D13% (9)