nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #70

The Project Board has three responsibilities towards the Management of Risk. Which of the following options is the FALSE one?

The correct answer is B. Ensuring that risks are identified, recorded and regularly reviewed. See the full explanation below for the reasoning.

Question

The Project Board has three responsibilities towards the Management of Risk. Which of the following options is the FALSE one?

Options

  • ANotifying the Project Manager of any external risk exposure to the project
  • BEnsuring that risks are identified, recorded and regularly reviewed
  • CMaking decisions on recommended reactions to risk
  • DStriking a balance between level of risk and potential benefits

How the community answered

(67 responses)
  • A
    9% (6)
  • B
    73% (49)
  • C
    4% (3)
  • D
    13% (9)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice