What environment does PRINCE2 assume?

The correct answer is B. A Customer/Supplier environment. See the full explanation below for the reasoning.

Question

What environment does PRINCE2 assume?

Options

  • AA fixed-price contract
  • BA Customer/Supplier environment
  • CA specialist environment
  • DA third-party environment

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    74% (35)
  • C
    6% (3)
  • D
    15% (7)