PRINCE2-FOUNDATION · Question #68
What element of PRINCE2 provides "an objective measurement for management progress control"?
The correct answer is A. Quality Review. See the full explanation below for the reasoning.
Question
What element of PRINCE2 provides “an objective measurement for management progress control”?
Options
- AQuality Review
- BCheckpoint Report
- CHighlight Report
- DEnd Stage Report
How the community answered
(55 responses)- A80% (44)
- B11% (6)
- C5% (3)
- D4% (2)