It would be chaotic to have the people who are working on the project starting activities whenever they think fit. What product does PRINCE2 use to control this?

The correct answer is B. Work Package. See the full explanation below for the reasoning.

Question

It would be chaotic to have the people who are working on the project starting activities whenever they think fit. What product does PRINCE2 use to control this?

Options

  • AProject Issue
  • BWork Package
  • CCheckpoint Report
  • DRisk Log

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    71% (22)
  • C
    16% (5)
  • D
    3% (1)