PRINCE2-FOUNDATION · Question #66
Which process covers the work required of people who may not be using PRINCE2?
The correct answer is D. Managing Product Delivery. See the full explanation below for the reasoning.
Question
Which process covers the work required of people who may not be using PRINCE2?
Options
- AManaging Stage Boundaries
- BStarting up a Project
- CDirecting a Project
- DManaging Product Delivery
How the community answered
(58 responses)- A10% (6)
- B5% (3)
- C3% (2)
- D81% (47)