PRINCE2-FOUNDATION · Question #593
Which should be used to document any uncompleted work that needs to be done, and any risks which need to be managed after the project has closed?
The correct answer is A. Follow-on action recommendations. See the full explanation below for the reasoning.
Question
Which should be used to document any uncompleted work that needs to be done, and any risks which need to be managed after the project has closed?
Options
- AFollow-on action recommendations
- BException Report
- CIssue Register
- DRisk Register
How the community answered
(37 responses)- A73% (27)
- B5% (2)
- C16% (6)
- D5% (2)