Which of the following is within the context of the Closing a Project process?
Options
- AProvide an opportunity to ensure that all unachieved goals and objectives are identified
- BProvide a means by which an exception process can be implemented
- CThe continuing correct focus of the project should be checked at the end of each stage
- DUsed for each delivery stage of the project