PRINCE2-FOUNDATION · Question #591

Which process would be triggered by the request to initiate a project?

The correct answer is D. Directing a Project. See the full explanation below for the reasoning.

Question

Which process would be triggered by the request to initiate a project?

Options

  • AStarting Up a Project
  • BControlling a Stage
  • CInitiating a Project
  • DDirecting a Project

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    10% (4)
  • C
    5% (2)
  • D
    81% (34)