PRINCE2-FOUNDATION · Question #594
Which is an objective of the Closing a Project process?
The correct answer is A. Provision has been made to address any open issues or risks with follow-on action. See the full explanation below for the reasoning.
Question
Which is an objective of the Closing a Project process?
Options
- AProvision has been made to address any open issues or risks with follow-on action
- BRequest authorization to start the next stage
- CPrepare an Exception Plan as directed by the Project Board
- DEnsure that the planned products are delivered to expectations and within tolerance
How the community answered
(54 responses)- A70% (38)
- B17% (9)
- C9% (5)
- D4% (2)