Question
Which is an objective of the Closing a Project process?
Options
- AProvision has been made to address any open issues or risks with follow-on action
- BRequest authorization to start the next stage
- CPrepare an Exception Plan as directed by the Project Board
- DEnsure that the planned products are delivered to expectations and within tolerance