PRINCE2-FOUNDATION · Question #594

Which is an objective of the Closing a Project process?

The correct answer is A. Provision has been made to address any open issues or risks with follow-on action. See the full explanation below for the reasoning.

Question

Which is an objective of the Closing a Project process?

Options

  • AProvision has been made to address any open issues or risks with follow-on action
  • BRequest authorization to start the next stage
  • CPrepare an Exception Plan as directed by the Project Board
  • DEnsure that the planned products are delivered to expectations and within tolerance

How the community answered

(54 responses)
  • A
    70% (38)
  • B
    17% (9)
  • C
    9% (5)
  • D
    4% (2)