PRINCE2-FOUNDATION · Question #511

Which of the following is a Project Board control?

The correct answer is B. Approve a Plan, with its relevant tolerances for the next management stage. See the full explanation below for the reasoning.

Question

Which of the following is a Project Board control?

Options

  • AApproving a deviation of benefits tolerance
  • BApprove a Plan, with its relevant tolerances for the next management stage
  • CReview Checkpoint Reports to monitor progress
  • DUse of project registers and logs to review progress

How the community answered

(48 responses)
  • A
    4% (2)
  • B
    75% (36)
  • C
    15% (7)
  • D
    6% (3)