PRINCE2-FOUNDATION · Question #511
Which of the following is a Project Board control?
The correct answer is B. Approve a Plan, with its relevant tolerances for the next management stage. See the full explanation below for the reasoning.
Question
Which of the following is a Project Board control?
Options
- AApproving a deviation of benefits tolerance
- BApprove a Plan, with its relevant tolerances for the next management stage
- CReview Checkpoint Reports to monitor progress
- DUse of project registers and logs to review progress
How the community answered
(48 responses)- A4% (2)
- B75% (36)
- C15% (7)
- D6% (3)