nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #512

Which level of management has control over a Work Package, as long as they are within the Work Package tolerances?

The correct answer is C. Team Manager. See the full explanation below for the reasoning.

Question

Which level of management has control over a Work Package, as long as they are within the Work Package tolerances?

Options

  • AProject Manager
  • BProject Board
  • CTeam Manager
  • DCorporate or programme management

How the community answered

(51 responses)
  • A
    16% (8)
  • B
    8% (4)
  • C
    73% (37)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice