PeopleCert
PRINCE2-FOUNDATION · Question #510
Which of the following is NOT within the authority of the Project Board?
The correct answer is D. Continuation where project-level tolerance is forecast to be exceeded. See the full explanation below for the reasoning.
Question
Which of the following is NOT within the authority of the Project Board?
Options
- ATrigger premature closure of the project
- BSetting stage-level tolerance
- CAuthorizing initiation
- DContinuation where project-level tolerance is forecast to be exceeded
How the community answered
(33 responses)- A9% (3)
- B6% (2)
- C3% (1)
- D82% (27)
Community Discussion
No community discussion yet for this question.