PRINCE2-FOUNDATION · Question #510

Which of the following is NOT within the authority of the Project Board?

The correct answer is D. Continuation where project-level tolerance is forecast to be exceeded. See the full explanation below for the reasoning.

Question

Which of the following is NOT within the authority of the Project Board?

Options

  • ATrigger premature closure of the project
  • BSetting stage-level tolerance
  • CAuthorizing initiation
  • DContinuation where project-level tolerance is forecast to be exceeded

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    6% (2)
  • C
    3% (1)
  • D
    82% (27)