What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?

The correct answer is C. Time-driven. See the full explanation below for the reasoning.

Question

What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?

Options

  • AEvent-driven
  • BException based
  • CTime-driven
  • DAd-hoc

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    77% (20)
  • D