What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?
The correct answer is C. Time-driven. See the full explanation below for the reasoning.
Question
What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?
Options
- AEvent-driven
- BException based
- CTime-driven
- DAd-hoc
How the community answered
(26 responses)- A4% (1)
- B12% (3)
- C77% (20)
- D8% (2)