The decision on whether a project's solution will be contracted to third parties is made in which product?

The correct answer is B. The Project Approach. See the full explanation below for the reasoning.

Question

The decision on whether a project’s solution will be contracted to third parties is made in which product?

Options

  • AThe Project Plan
  • BThe Project Approach
  • CThe Project Brief
  • DThe Project Quality Plan

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    85% (23)
  • C
    4% (1)
  • D
    7% (2)