PeopleCert
PRINCE2-FOUNDATION · Question #50
The decision on whether a project's solution will be contracted to third parties is made in which product?
The correct answer is B. The Project Approach. See the full explanation below for the reasoning.
Question
The decision on whether a project’s solution will be contracted to third parties is made in which product?
Options
- AThe Project Plan
- BThe Project Approach
- CThe Project Brief
- DThe Project Quality Plan
How the community answered
(27 responses)- A4% (1)
- B85% (23)
- C4% (1)
- D7% (2)
Community Discussion
No community discussion yet for this question.