PRINCE2-FOUNDATION · Question #49

New versions of the Project Plan are produced at the end of each stage to reflect updated information. Identify which option is FALSE.

The correct answer is B. Benefits already achieved. See the full explanation below for the reasoning.

Question

New versions of the Project Plan are produced at the end of each stage to reflect updated information. Identify which option is FALSE.

Options

  • AProgress already made
  • BBenefits already achieved
  • CAny agreed changes in circumstances
  • DAny revised forecast of cost

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    79% (38)
  • C
    2% (1)
  • D
    13% (6)

Community Discussion

No community discussion yet for this question.