PRINCE2-FOUNDATION · Question #51
Apart from "Initiating a Project" in which process is the Business Case updated?
The correct answer is C. Managing Stage Boundaries. See the full explanation below for the reasoning.
Question
Apart from “Initiating a Project” in which process is the Business Case updated?
Options
- AManaging Product Delivery
- BControlling a Stage
- CManaging Stage Boundaries
- DAuthorising a Stage
How the community answered
(55 responses)- A5% (3)
- B11% (6)
- C82% (45)
- D2% (1)