PRINCE2-FOUNDATION · Question #43
Fromtheproductslisted,which one i s produced during' Starting Up a Project'?
The correct answer is D. The Project Approach. See the full explanation below for the reasoning.
Question
Fromtheproductslisted,which one i s produced during‘ Starting Up a Project’?
Options
- AThe Project Initiation Document
- BThe Project Plan
- CThe Project Quality Plan
- DThe Project Approach
How the community answered
(13 responses)- A8% (1)
- B15% (2)
- C8% (1)
- D69% (9)
Community Discussion