PRINCE2-FOUNDATION · Question #44
Quality responsibilities, both within and external to the project, are defined in which process?
The correct answer is A. Initiating a Project. See the full explanation below for the reasoning.
Question
Quality responsibilities, both within and external to the project, are defined in which process?
Options
- AInitiating a Project
- BStarting up a Project
- CManaging Stage Boundaries
- DDirecting a Project
How the community answered
(24 responses)- A83% (20)
- B4% (1)
- C4% (1)
- D8% (2)