PeopleCert
PRINCE2-FOUNDATION · Question #42
Which process checks for changes to the project management team?
The correct answer is B. Managing Stage Boundaries. See the full explanation below for the reasoning.
Question
Which process checks for changes to the project management team?
Options
- AStarting up a Project
- BManaging Stage Boundaries
- CClosing a Project
- DDirecting a Project
How the community answered
(44 responses)- A5% (2)
- B80% (35)
- C5% (2)
- D11% (5)