What is the purpose of the risk budget?
Options
- ATo fund risk management activities defined in the risk management procedure
- BTo fund the cost of analyzing requests for change while executing a Work Package
- CFunds set aside from the project budget to cover the costs of implementing risk responses
- DFunds set aside from the project budget to cover the costs of identifying risks to the project