PRINCE2-FOUNDATION · Question #277

Which of the following are valid risk responses for threats?

The correct answer is C. Avoid, Accept, Fallback. See the full explanation below for the reasoning.

Question

Which of the following are valid risk responses for threats?

Options

  • AAccept, Enhance, Transfer
  • BAvoid, Enhance, Fallback
  • CAvoid, Accept, Fallback
  • DExploit, Accept, Fallback

How the community answered

(52 responses)
  • A
    13% (7)
  • B
    4% (2)
  • C
    75% (39)
  • D
    8% (4)