Which statement describes risk cause?

The correct answer is B. The situation or event that gave rise to a risk. See the full explanation below for the reasoning.

Question

Which statement describes risk cause?

Options

  • AThe impact of a risk on the stage and project tolerance
  • BThe situation or event that gave rise to a risk
  • CThe area of uncertainty in terms of the threat or opportunity
  • DHow likely a risk is to occur in a given project situation

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    81% (42)
  • C
    12% (6)
  • D
    6% (3)