PRINCE2-FOUNDATION · Question #190

What plan identifies quality responsibilities for the project?

The correct answer is C. the Project Quality Plan. See the full explanation below for the reasoning.

Question

What plan identifies quality responsibilities for the project?

Options

  • AThe Project Plan
  • Ba Stage Quality Plan
  • Cthe Project Quality Plan
  • Da Team Plan

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    9% (4)
  • C
    84% (38)
  • D
    4% (2)