In which process does the Project Manager ask the Project Board where the authority for making change lies?

The correct answer is B. During Initiating a Project. See the full explanation below for the reasoning.

Question

In which process does the Project Manager ask the Project Board where the authority for making change lies?

Options

  • ADuring Starting Up A Project
  • BDuring Initiating a Project
  • CIn Giving Ad Hoc Direction
  • DWhen Authorising a Stage

How the community answered

(46 responses)
  • A
    9% (4)
  • B
    83% (38)
  • C
    7% (3)
  • D
    2% (1)