In which process does the Project Manager ask the Project Board where the authority for making change lies?
The correct answer is B. During Initiating a Project. See the full explanation below for the reasoning.
Question
In which process does the Project Manager ask the Project Board where the authority for making change lies?
Options
- ADuring Starting Up A Project
- BDuring Initiating a Project
- CIn Giving Ad Hoc Direction
- DWhen Authorising a Stage
How the community answered
(46 responses)- A9% (4)
- B83% (38)
- C7% (3)
- D2% (1)