PeopleCert
PRINCE2-FOUNDATION · Question #189
PRINCE2-FOUNDATION Question #189: Real Exam Question with Answer & Explanation
The correct answer is B. Checkpoint Report. See the full explanation below for the reasoning.
Question
What time-driven control ascertains the status of team members' work?
Options
- AHighlight Report
- BCheckpoint Report
- CException Report
- DEnd Stage Report
Community Discussion