Which product does PRINCE2 suggest should include the budget and schedule impact of changes?

The correct answer is C. Highlight Report. See the full explanation below for the reasoning.

Question

Which product does PRINCE2 suggest should include the budget and schedule impact of changes?

Options

  • ACheckpoint Report
  • BException Report
  • CHighlight Report
  • DLessons Learned Report

How the community answered

(32 responses)
  • A
    13% (4)
  • B
    3% (1)
  • C
    75% (24)
  • D
    9% (3)