PRINCE2-FOUNDATION · Question #187

Are the majority of PRINCE2TM controls described as...?

The correct answer is A. Event-driven. See the full explanation below for the reasoning.

Question

Are the majority of PRINCE2TM controls described as...?

Options

  • AEvent-driven
  • BTime-driven
  • CAd hoc
  • DTechnique-based

How the community answered

(27 responses)
  • A
    78% (21)
  • B
    11% (3)
  • C
    4% (1)
  • D
    7% (2)