What is a concession?
The correct answer is C. An Off-Specification accepted by the Project Board without corrective action. See the full explanation below for the reasoning.
Question
What is a concession?
Options
- AA contract to a third party
- BAn error found in a Quality Review which is not corrected
- CAn Off-Specification accepted by the Project Board without corrective action
- DAn allowance above and beyond tolerance levels
How the community answered
(59 responses)- A5% (3)
- B10% (6)
- C81% (48)
- D3% (2)
Community Discussion