What is a concession?

The correct answer is C. An Off-Specification accepted by the Project Board without corrective action. See the full explanation below for the reasoning.

Question

What is a concession?

Options

  • AA contract to a third party
  • BAn error found in a Quality Review which is not corrected
  • CAn Off-Specification accepted by the Project Board without corrective action
  • DAn allowance above and beyond tolerance levels

How the community answered