If there were a need to know what the precise content of an old version of a product was, what part of PRINCE2TM would most help us?
The correct answer is C. Configuration Management. See the full explanation below for the reasoning.
Question
If there were a need to know what the precise content of an old version of a product was, what part of PRINCE2TM would most help us?
Options
- AThe Stage Plan
- BThe Issue Log
- CConfiguration Management
- DWork Package Authorisations
How the community answered
(25 responses)- A4% (1)
- B8% (2)
- C72% (18)
- D16% (4)