Question

There are several benefits that the end stage assessment brings to a project. Which one of the following is NOT a benefit?

Options

  • ATo enable the approval of an Exception Report
  • BTo provide a review of a risky project at key moments when new information about those
  • CTo ensure that key decisions are made prior to the detailed work needed to implement them
  • DTo provide a' fire break' for the project by encouraging the Project Board to assess the

Unlock PRINCE2-FOUNDATION to see the answer