The correct answer is B. From the problem to the end of a plan that will no longer finish within agreed tolerances. See the full explanation below for the reasoning.

Question

An Exception Plan covers what period?

Options

  • AFrom the problem to the end of the project
  • BFrom the problem to the end of a plan that will no longer finish within agreed tolerances
  • CThe work needed to put the project back within its tolerances
  • DThe time needed to produce an Exception Report