An Exception Plan covers what period?
The correct answer is B. From the problem to the end of a plan that will no longer finish within agreed tolerances. See the full explanation below for the reasoning.
Question
An Exception Plan covers what period?
Options
- AFrom the problem to the end of the project
- BFrom the problem to the end of a plan that will no longer finish within agreed tolerances
- CThe work needed to put the project back within its tolerances
- DThe time needed to produce an Exception Report
How the community answered
(17 responses)- A12% (2)
- B76% (13)
- C6% (1)
- D6% (1)
Community Discussion
No community discussion yet for this question.