PeopleCert
PRINCE2-FOUNDATION · Question #16
PRINCE2-FOUNDATION Question #16: Real Exam Question with Answer & Explanation
The correct answer is B. From the problem to the end of a plan that will no longer finish within agreed tolerances. See the full explanation below for the reasoning.
Question
An Exception Plan covers what period?
Options
- AFrom the problem to the end of the project
- BFrom the problem to the end of a plan that will no longer finish within agreed tolerances
- CThe work needed to put the project back within its tolerances
- DThe time needed to produce an Exception Report
Community Discussion
No community discussion yet for this question.