PRINCE2-FOUNDATION · Question #18
The initial Project Plan is based on the Project Brief, the Project Quality Plan and which other product?
The correct answer is A. The Project Approach. See the full explanation below for the reasoning.
Question
The initial Project Plan is based on the Project Brief, the Project Quality Plan and which other product?
Options
- AThe Project Approach
- BThe Project Initiation Document
- CThe project start-up notification
- DThe Project Mandate
How the community answered
(30 responses)- A73% (22)
- B3% (1)
- C7% (2)
- D17% (5)