PeopleCert
PRINCE2-FOUNDATION · Question #1065
What is established during the 'initiating a project' process?
The correct answer is A. The agreed protect acceptance criteria. See the full explanation below for the reasoning.
Question
What is established during the 'initiating a project' process?
Options
- AThe agreed protect acceptance criteria
- BThe need for a configuration library
- CA plan for the work or project initiation
- DAn understanding of the project's funding
How the community answered
(39 responses)- A74% (29)
- B8% (3)
- C5% (2)
- D13% (5)
Community Discussion
No community discussion yet for this question.