nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #1065

What is established during the 'initiating a project' process?

The correct answer is A. The agreed protect acceptance criteria. See the full explanation below for the reasoning.

Question

What is established during the 'initiating a project' process?

Options

  • AThe agreed protect acceptance criteria
  • BThe need for a configuration library
  • CA plan for the work or project initiation
  • DAn understanding of the project's funding

How the community answered

(39 responses)
  • A
    74% (29)
  • B
    8% (3)
  • C
    5% (2)
  • D
    13% (5)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice