Which is an objective of the 'directing a project' process?
The correct answer is B. To select and appoint the project manager. See the full explanation below for the reasoning.
Question
Which is an objective of the 'directing a project' process?
Options
- ATo create the plan to deliver the project product
- BTo select and appoint the project manager
- CTo design the project management team roles
- DTo give authority to deliver the project product
How the community answered
(38 responses)- A5% (2)
- B71% (27)
- C16% (6)
- D8% (3)