Which is an objective of the 'directing a project' process?

The correct answer is B. To select and appoint the project manager. See the full explanation below for the reasoning.

Question

Which is an objective of the 'directing a project' process?

Options

  • ATo create the plan to deliver the project product
  • BTo select and appoint the project manager
  • CTo design the project management team roles
  • DTo give authority to deliver the project product

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    71% (27)
  • C
    16% (6)
  • D
    8% (3)