PRINCE2-FOUNDATION · Question #1066
Which is an objective of the 'controlling a stage' process?
The correct answer is D. To produce a learn plan for the work package. See the full explanation below for the reasoning.
Question
Which is an objective of the 'controlling a stage' process?
Options
- ATo review the business justification for the project
- BTo replan the current stage when directed
- CTo develop products to defined quality criteria
- DTo produce a learn plan for the work package
How the community answered
(31 responses)- A10% (3)
- B3% (1)
- C6% (2)
- D81% (25)