Which action should the project manager take during the 'assessing issues' step?
The correct answer is D. Determine the initial priority of the issue that has been raised. See the full explanation below for the reasoning.
Question
Which action should the project manager take during the 'assessing issues' step?
Options
- ACreate an exception plan tor project board approval
- BGain project board feedback on the Issue priority
- CConsider the impact of alternative options for resolution
- DDetermine the initial priority of the issue that has been raised
How the community answered
(36 responses)- A14% (5)
- B6% (2)
- C6% (2)
- D75% (27)