Which is a minimum requirement for applying the 'change' theme?

The correct answer is C. Produce issue reports to document the impact assessment for requests for change. See the full explanation below for the reasoning.

Question

Which is a minimum requirement for applying the 'change' theme?

Options

  • ASpecify in the change control approach the means by which project products will be protected
  • BDocument the format and contents of the issue register
  • CProduce issue reports to document the impact assessment for requests for change
  • DDelegate the change authority to the senior supplier(s) for supplier off-specifications

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    84% (31)
  • D
    8% (3)