Which report must be used to inform the project board of a predicted deviation from agreed stage limits?
The correct answer is D. Exception report. See the full explanation below for the reasoning.
Question
Which report must be used to inform the project board of a predicted deviation from agreed stage limits?
Options
- AEnd stage report
- BCheckpoint report
- CHighlight report
- DException report
How the community answered
(20 responses)- A15% (3)
- B5% (1)
- C5% (1)
- D75% (15)