Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

The correct answer is D. Exception report. See the full explanation below for the reasoning.

Question

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

Options

  • AEnd stage report
  • BCheckpoint report
  • CHighlight report
  • DException report

How the community answered

(20 responses)
  • A
    15% (3)
  • B
    5% (1)
  • C
    5% (1)
  • D
    75% (15)